Author(s):     
 
Lumetzberger, Martin; Kitzler, Christian
 
Title:     
 

 
Abstract:     
 
The “KW Bärenwerk” power station project is currently being implemented by the Salzburg AG. This article reports in detail how extensive surveys of the existing condition formed the basis for innovative decisions making by the company. The investigations carried out above and below ground in the period 2009-2010 were the basis for an objective consideration of the decision whether to repair the existing tunnel system or construct a new tunnel.
First the power station and its current facilities are described, with particular emphasis on the headrace and headrace tunnel. The investigations and analyses are also described in detail, and how the knowledge gained was used in the design process. A possible decision-making process is described, with a comparison of the most important features in order to differentiate between repair and new construction. The report ends with the state of the works that are currently underway.
In diesem Beitrag wird an einem derzeit in Realisierung befindlichem Kraftwerksprojekt “KW Bärenwerk” der Salzburg AG ausführlich dargelegt, wie eine umfassende Bestandserhebung die Grundlage zu einer richtungsweisenden Unternehmensentscheidungen bilden kann. Die unter- sowie obertägig im Zeitraum von 2009 und 2010 durchgeführten Untersuchungen waren die Basis für eine objektive Betrachtungsweise der beiden möglichen Entscheidungswege einer Sanierung des bestehenden Stollensystems oder eines Stollenneubaus.
Einleitend werden das Kraftwerk mit seinen Anlagenteilen und die Ist-Situation erläutert, wobei speziell auf den Triebwasserweg bzw. den Triebwasserstollen eingegangen wird. Weiter werden die Untersuchungen und Analysen detailliert beschrieben und die daraus gewonnen Erkenntnisse in die Planung übertragen. Es wird ein möglicher Weg des Entscheidungsprozesses gezeigt und dazu anhand einer Gegenüberstellung der wesentlichsten Entscheidungskriterien die wichtigsten Unterscheidungsmerkmale der Sanierung bzw. des Neubaus des Druckstollens dargelegt. Der Bericht schließt mit dem Stand der tatsächlich durchgeführten Arbeiten.
 
Source:     Geomechanics and Tunnelling 6 (2013), No. 5
 
Page/s:     434-445
 
Language of Publication:     English/German



I would like to buy the article

You can download this article for 25 € as a PDF file (0.64 MB).
The PDF file can be read, printed and saved.
Duplication and forwarding to third parties is not allowed.


Please enter your email address now to start the order process.
The link for the download will be sent to the email address stated after the
order process has been completed.

Your email address


I am an online subscriber

As an online subscriber of the journal "Geomechanics and Tunnelling" you can access this article via Wiley Online Library.

I would like to order "Geomechanics and Tunnelling"

This article has been published in the journal "Geomechanics and Tunnelling". If you would like to learn more about the journal, you can order a free sample copy or find out more information on our website.


Prices include VAT and postage. Prices for 2017/2018.
€ Prices apply to Germany only. Subject to alterations, errors excepted.